🎓 Prepared by students from Boğaziçi University

What is Net Present Value (NPV)?

Net Present Value (NPV) measures whether an investment or project is worth pursuing by discounting all its future cash flows back to today's dollars and subtracting the initial cost. A positive NPV means the investment is expected to add value.

Short answer

NPV is the sum of all a project's future cash flows discounted to present value, minus the initial investment; NPV = Σ CFt/(1+r)^t − C0. If NPV > 0, the investment is expected to be profitable.

How to calculate NPV
  1. 1
    1. Forecast cash flows
    Estimate the expected cash flow for every future period of the project.
  2. 2
    2. Choose a discount rate
    Pick r — usually the cost of capital or required rate of return.
  3. 3
    3. Discount each cash flow
    Divide each period's cash flow by (1+r)^t to bring it to today's value.
  4. 4
    4. Sum the discounted flows
    Add all discounted cash flows together.
  5. 5
    5. Subtract the initial cost
    NPV = sum of discounted flows − initial investment C0.
  6. 6
    6. Decide
    NPV > 0 → accept the project; NPV < 0 → reject it.
01

Try it: interactive calculator

Net present value (single cash flow)
208.75$
= -10,000 + 15,000/(1+8/100)^5
02

Step-by-step worked examples

A project costs $10,000 today and returns a single cash flow of $15,000 in 5 years. At an 8% discount rate, what is the NPV?

NPV = -C0 + CF/(1+r)^t
NPV = -10000 + 15000/(1.08)^5
(1.08)^5 ≈ 1.4693
NPV = -10000 + 15000/1.4693 ≈ -10000 + 10208.80 = $208.80
Since NPV > 0, the project is worth pursuing

A project costs $50,000 today and produces cash flows of $20,000 at the end of each of the next 3 years. At a 10% discount rate, what is the NPV?

NPV = -C0 + CF1/(1+r)^1 + CF2/(1+r)^2 + CF3/(1+r)^3
NPV = -50000 + 20000/1.10 + 20000/1.21 + 20000/1.331
NPV = -50000 + 18181.82 + 16528.93 + 15026.30
NPV = -50000 + 49737.05 = -$262.95
Since NPV < 0, the project should be rejected

Two projects both cost $5,000. Project A returns $6,500 in 2 years; Project B returns $7,000 in 4 years. At a 6% discount rate, which has the higher NPV?

Project A: NPV = -5000 + 6500/(1.06)^2 = -5000 + 6500/1.1236 ≈ -5000 + 5785.26 = $785.26
Project B: NPV = -5000 + 7000/(1.06)^4 = -5000 + 7000/1.26248 ≈ -5000 + 5545.28 = $545.28
Project A has the higher NPV ($785.26 > $545.28), so it's the better choice
03

Flashcards

04

Quick quiz

Q1.A project has NPV = $500. What should you do?

Correct answer: B. A positive NPV means the project adds value above the discount rate — generally accept.

Q2.In the NPV formula, what does C0 represent?

Correct answer: C. C0 is the upfront cost of the investment, subtracted from the sum of discounted cash flows.

Q3.If the discount rate increases, what typically happens to NPV (holding cash flows fixed)?

Correct answer: B. A higher discount rate shrinks the present value of future cash flows, lowering NPV.

Q4.Between two mutually exclusive projects, which is generally preferred?

Correct answer: B. NPV directly measures value added, so the project with the higher NPV is generally preferred.
📄Download this topic as a printable worksheet (PDF)Summary + 10 questions + answer key — print it, share it in class.
Study better with Bounlu apps
Notek
Notek

The full card deck, worked steps and AI-tutor support for “What is Net Present Value (NPV)?” are in Notek — study by hand before your exam.

Get it free
Notek 1Notek 2Notek 3Notek 4Notek 5
05

Common mistakes

Comparing raw future cash flows without discounting them.Correct: Cash flows at different times must be discounted to present value before comparing them.

Forgetting to subtract the initial investment C0.Correct: NPV is the discounted cash flows MINUS the upfront cost — not just the sum of discounted inflows.

Using the wrong discount rate (e.g. an arbitrary number).Correct: Use the project's true cost of capital or required rate of return as r.

Thinking NPV = 0 means a bad investment.Correct: NPV = 0 means the project exactly meets the required rate of return — it's break-even, not bad.

06

FAQ

What is Net Present Value (NPV)?

NPV is a project's discounted future cash flows minus its initial cost, showing how much value it's expected to add.

What is the NPV formula?

NPV = Σ [CFt/(1+r)^t] − C0, where CFt is the cash flow in period t, r is the discount rate, and C0 is the initial investment.

How do you calculate NPV?

Discount each future cash flow back to present value using (1+r)^t, sum them, then subtract the initial investment.

What are examples of NPV in practice?

Companies use NPV to decide whether to build a new factory, launch a product, or invest in equipment — accepting projects with NPV > 0.

Related topics